Calendar showing the narrowing window between now and 28 February 2027 for commissioning a solar or BESS project to qualify for the Section 12B tax deduction
    Financing

    FY27 Tax Deadline: Why End October 2026 Is the Last Realistic Window to Act on Solar

    12 September 2026 · Forest Energy

    Back to Blogs & Articles

    If your financial year ends in February 2027, you have a narrow window to commission a solar or battery project and claim a 100% Section 12B tax deduction. Projects take 3 to 6 months from contract to commissioning. The end of October 2026 is the last realistic point to sign.

    Section 12B is not a once-off incentive. It applies every tax year, and that can create a false sense of time. The deduction falls in the year the system is brought into use, so for any business with a financial year end of 28 February 2027, the system has to be running before that date. Working back from project lead times, the effective deadline to sign is the end of October 2026.

    Miss that window and you do not lose the incentive entirely, but you lose a full year of tax benefit in a year where you may have the income to absorb it. For some businesses, that delay costs more than the financing would have.

    How the Section 12B deduction actually works

    Section 12B of the Income Tax Act allows a business to deduct 100% of the cost of a qualifying renewable energy asset in the year the asset is first brought into use. Brought into use means the system is fully commissioned and generating electricity, not just contracted or installed.

    For a business with a 28 February year end, that means the plant needs to be running before the financial year closes. Not signed. Not permitted. Not under construction. Running.

    On a system costing R5 million, a 100% deduction in year one reduces taxable income by R5 million. At a 27% corporate tax rate, that is a R1.35 million tax saving in a single year. That saving either improves payback materially or, on financed projects, can be structured to reduce the repayment burden.

    Why the end of October 2026 is the last realistic window

    Commercial solar and battery projects take time. From contract signature to commissioning, a straightforward rooftop solar installation typically takes 3 to 4 months. A hybrid solar plus BESS project, or any site with grid application requirements, connection upgrades, or structural complexity, takes 4 to 6 months. Some take longer.

    Working backwards from 28 February 2027:

    • A project signed by the end of October 2026 has about 4 months to commission, enough for a straightforward rooftop system with little margin
    • A project signed in November 2026 would need to commission in around 3 months, which is only possible for the simplest sites
    • A project signed in December 2026 or later cannot realistically be commissioned before the February deadline

    Signing by the end of October gives a project about four months to run. That is not a comfortable buffer. It is the minimum realistic window for a straightforward commercial rooftop system, and a hybrid solar plus BESS project, which typically takes 4 to 6 months, may already be too tight for FY27. If that is your situation, the deduction is not lost. Section 12B applies again in FY28, as long as the system is running before your next year end.

    The PPA argument is separate but equally time-sensitive

    Not every business can deploy capital right now, and not every business needs to. A Power Purchase Agreement (PPA) lets Forest Energy fund, install, and maintain the system, and the client pays only for the electricity generated, at an agreed rate, typically below the current grid tariff.

    The Section 12B deduction does not apply to you under a PPA structure, because you do not own the asset. But there is a separate and compelling reason to move now: rate locking.

    Every Eskom tariff increase, and every municipal tariff adjustment, makes the renewable rate look more competitive against whatever you signed. Locking in a PPA rate now, before the next increase cycle, sets your baseline at today's tariff environment. Waiting 6 or 12 months means your new contract rate is benchmarked against a higher grid tariff, which narrows the saving.

    Both the CAPEX case and the PPA case improve with time. Neither benefits from waiting.

    What the tax deduction looks like at different system sizes

    Indicative capital costSection 12B deduction (100%)Tax saving at 27% corporate rate
    System 1R 1.8MR 1.8MR 486 000
    System 2R 3.2MR 3.2MR 864 000
    System 3R 5.5MR 5.5MR 1 485 000
    System 4R 8.5MR 8.5MR 2 295 000

    These are illustrative figures based on typical commercial project costs. Actual costs depend on site complexity, equipment specification, grid requirements, and mounting structure. The tax saving is the deduction multiplied by your effective tax rate, which can be modelled precisely once we have your financial year end and taxable income profile.

    Qualifying criteria to keep in mind

    • The asset must be new and unused, not second-hand or refurbished
    • The system must be used in the production of income, not purely domestic or off-grid
    • The full system, solar PV, inverters, and BESS if included, must be commissioned before your financial year end
    • SARS may request commissioning documentation, so a professional sign-off is essential

    SARS has been clear that commissioning date is the determining factor. A system that is not commissioned and producing on 28 February 2027 does not qualify for the February 2027 year-end deduction. This is why the timeline is not a preference, it is a hard requirement.

    What to do right now

    If your financial year ends in February 2027 and you have been considering a solar or BESS project, the decision window is closing. The first step is a site assessment and financial model, not a commitment. That process takes a few days and tells you exactly what the system would cost, what it saves, what the tax impact looks like, and whether your site can be commissioned before the deadline.

    If the answer is yes, the next step is moving quickly. Engineering, procurement, and installation all have lead times, and the earlier the contract is in place, the more delivery margin we have.

    Contact Forest Energy before the end of October. We will give you an honest assessment of whether February 2027 is achievable for your site, what it would take to get there, and what the business case looks like. No obligation. Just clarity.

    Common questions

    What is the Section 12B tax deduction for solar?

    Section 12B of the Income Tax Act allows businesses to deduct 100% of the cost of a qualifying renewable energy asset in the year it is brought into use. It is a standing allowance, not a once-off incentive, so it is available every tax year. What sets your deadline is your financial year end: the system must be commissioned before it to claim in that year.

    Does the plant need to be commissioned before my financial year end to qualify?

    Yes. The deduction applies in the year the asset is first brought into use. If your financial year ends 28 February 2027, the system must be fully commissioned and generating electricity before that date.

    How long does a commercial solar or BESS project take?

    From signed contract to commissioning, most commercial projects take between 3 and 6 months. Larger or more complex sites can take longer. A project signed after the end of October 2026 is unlikely to be commissioned before the February 2027 deadline.

    What is PPA rate locking and why does it matter now?

    A Power Purchase Agreement fixes the rate you pay for solar energy over the agreement term, typically 10 to 20 years. Signing now locks you into today's rate before the next Eskom or municipal tariff increase. Waiting means your PPA rate baseline is higher.

    What should I do right now if I want to act before the deadline?

    Contact Forest Energy before the end of October 2026. We will assess your site, model the business case, and give you an honest read on whether commissioning before 28 February 2027 is achievable given your site complexity. The earlier we start, the more margin we have.

    Related solution

    Fully Financed Solutions

    Solar and BESS with zero upfront capital through PPAs and battery rental.

    Take control of your energy strategy

    Let our engineering team design a tailored solution aligned to your operational needs, cost structure, and long-term growth.